Large area Copy/Paste in TM1 Perspective

Post Reply
David Lee
Posts: 10
Joined: Wed Jan 05, 2011 4:37 pm
OLAP Product: TM1
Version: V9.5.1
Excel Version: MS Excel 2003
Location: Taipei, Taiwan

Large area Copy/Paste in TM1 Perspective

Post by David Lee »

Hi all,

In TM1 Perspective user can input data on each cell and the DBRW function will send the value back to TM1 server. We would like to know if it is possible to copy data of a large area, for example, A1:D10 in one sheet and paste the data to another sheet with DBRW formula on the cells. However, when we pasted data, the DBRW formula is replaced by the values. Does anyone know how to avoid this problem? Or is this a product limitation?

Thanks in advance for your help!
Alan Kirk
Site Admin
Posts: 6654
Joined: Sun May 11, 2008 2:30 am
OLAP Product: TM1
Version: PA2.0.9.18 Classic NO PAW!
Excel Version: 2013 and Office 365
Location: Sydney, Australia
Contact:

Re: Large area Copy/Paste in TM1 Perspective

Post by Alan Kirk »

David Lee wrote: In TM1 Perspective user can input data on each cell and the DBRW function will send the value back to TM1 server. We would like to know if it is possible to copy data of a large area, for example, A1:D10 in one sheet and paste the data to another sheet with DBRW formula on the cells. However, when we pasted data, the DBRW formula is replaced by the values. Does anyone know how to avoid this problem? Or is this a product limitation?
It's a product limitation which some of us got sick of waiting for Iboglix to address.

You'll therefore find it in TM1 Tools, which can be downloaded from here.
"To them, equipment failure is terrifying. To me, it’s 'Tuesday.' "
-----------
Before posting, please check the documentation, the FAQ, the Search function and FOR THE LOVE OF GLUB the Request Guidelines.
kpk
MVP
Posts: 214
Joined: Tue Nov 11, 2008 11:57 pm
OLAP Product: TM1, CX
Version: TM1 7x 8x 9x 10x CX 9.5 10.1
Excel Version: XP 2003 2007 2010
Location: Hungary

Re: Large area Copy/Paste in TM1 Perspective

Post by kpk »

There are some other workarounds:
1) use DBS to send the data back to the TM1 server
2) copy value into CubeViewer
3) publish your Excel to TM1web where the user can copy paste more than one cell into TM1 (as far as I remember)
Best Regards,
Peter
Post Reply