Cannot Copy Value With Properly Using Turbo Integrator
Posted: Mon Aug 03, 2015 7:46 am
Dear All,
I need help here..
I've made to copy value in cognos tm1 in Bottom Up Version. I copied the value in Budget 1 to Budget 2 in the same Cube. But the problem is the process cannot copy the value with properly in Top Down Version. In my Top Down Version some of the Cube has three to eight view, I create the rule same like what i did in Bottom Up Version.
But some column didn't show the value and when i change the value in budget 1 that didn't replace the value that has copied in budget 2
Anyone know what should i do ?Is that the feeders or something ? Has anyone have the same problem with me and can fix it .. ???
I've tried to make process for each view but it doesn't work . the result still same . I use View as my datasource.
Thanks and Regards
Chita
I need help here..
I've made to copy value in cognos tm1 in Bottom Up Version. I copied the value in Budget 1 to Budget 2 in the same Cube. But the problem is the process cannot copy the value with properly in Top Down Version. In my Top Down Version some of the Cube has three to eight view, I create the rule same like what i did in Bottom Up Version.
But some column didn't show the value and when i change the value in budget 1 that didn't replace the value that has copied in budget 2
Anyone know what should i do ?Is that the feeders or something ? Has anyone have the same problem with me and can fix it .. ???
I've tried to make process for each view but it doesn't work . the result still same . I use View as my datasource.
Thanks and Regards
Chita