Hi,
I need to a create TI process to calculate percentage on current day value and previous day values on a dimension elements- Only for few elements-not all elements.
And I need to trigger exception email to notice percentage have changed between current day and previous day.
My questions are:
1) In Data tab I am able to achieve the results -by each line items as the percentage calculation each elements are different - how do I combine all elements to achieve it?
2) Trigger exception email - in Prolog tab- what would be general code- I need to think of.
Thanks
Rb
TI Process
-
- Regular Participant
- Posts: 424
- Joined: Sat Mar 10, 2012 1:03 pm
- OLAP Product: IBM TM1, Planning Analytics, P
- Version: PAW 2.0.8
- Excel Version: 2019
Re: TI Process
It might be not exactly what you been looking for ,But you will get the gist of it.
http://www.tm1forum.com/viewtopic.php?t=1785
http://www.tm1forum.com/viewtopic.php?t=8194 Thanks
http://www.tm1forum.com/viewtopic.php?t=1785
http://www.tm1forum.com/viewtopic.php?t=8194 Thanks